M.E Engineering Beer Process Vessels

Beer Process Vessels

beer storage vessels
500 kL pressure vessels on dock at White Bay NSW
beer storage vessels
Pressure vessels are barged up the Parramatta River
beer storage vessels
Vessels are loaded onto trucks for the final leg of the journey to site
beer storage vessels
Road transportation completed overnight to minimise traffic disruption
beer storage vessels
Legs are installed on the vertical storage vessels
beer storage vessels
250 tonne & 350 tonne cranes are used to lift the vertical tanks
beer storage vessels
350 tonne crane positions the tank and lowers it in place
beer storage vessels
500 kL horizontal process vessel is lifted onto steel housing
beer storage vessels
New storage tanks installed, piped and ready for commissioning
This project was a complex transportation and installation job to increase the beer storage capacities of an existing plant in NSW. It required coordination between the transport companies, traffic authorities and site personnel. A major public road needed to be closed during the job. Site access for other users during unloading, ground conditions and the installation of the oversize tanks all had to be considered to minimise future lifting operations and disruption of other activities on site. The installation included automation of the new beer process vessels and was scheduled to ensure that no major plant shutdown was required.

Other Beverage Projects

brewery  beer production  carbonated soft drinks